=== | ===Upcoming Events=== | ||
===Project Tasks=== | ===Project Tasks=== | ||
| Line 13: | Line 10: | ||
* [[Brew_Hut_Rebuild/Finish the hut|Finish the hut]] | * [[Brew_Hut_Rebuild/Finish the hut|Finish the hut]] | ||
===Completed Project Tasks=== | ===Completed Project Tasks=== | ||
* [[Brew Hut Cleanup|Workhike to build outhouse and clean up garbage]] July 22-23, 2006 | |||
* Build Woodshed / Foundations for stairs / fly out garbage September 2006. | |||
* Build Outhouse July 2006 | |||
* [[Brew_Hut_Rebuild/Final_Workhike|Final Workhike (for 2005)]] ''workhike October 29-30 to finish the interior and build the deck and stairs'' | |||
* [[Brew_Hut_Rebuild/Remove the old hut|Remove the old hut]] ''We did this on September 24-25 weekend'' | * [[Brew_Hut_Rebuild/Remove the old hut|Remove the old hut]] ''We did this on September 24-25 weekend'' | ||
* [[Brew Hut Rebuild/Planning-Scheduling| Planning-Scheduling]] - JP | * [[Brew Hut Rebuild/Planning-Scheduling| Planning-Scheduling]] - JP | ||
| Line 26: | Line 27: | ||
* [[Brew Hut Rebuild/Transport|Transport]] - JP | * [[Brew Hut Rebuild/Transport|Transport]] - JP | ||
* [[Brew Hut Rebuild/Helicopter|Helicopter]] - JP | * [[Brew Hut Rebuild/Helicopter|Helicopter]] - JP | ||
* [[Brew_Hut_Rebuild/Build the outhouse|Build the outhouse]] | |||
===Other stuff=== | ===Other stuff=== | ||
| Line 52: | Line 54: | ||
* [[Brew Hut Rebuild/July 30|July 30]] - the great brew build - part 2 | * [[Brew Hut Rebuild/July 30|July 30]] - the great brew build - part 2 | ||
* [[Brew Hut Rebuild/September 24|September 24]] - the deconstruction of the old brew hut (brew 2) | * [[Brew Hut Rebuild/September 24|September 24]] - the deconstruction of the old brew hut (brew 2) | ||
* [[Brew_Hut_Rebuild/Final_Workhike|October 29]] - final 2005 workhike | |||
==New Brew Trail== | ==New Brew Trail== | ||
A new trail | A new trail is part of the plan for the new hut. See the wiki page for [[Brew Hut Trail Upgrade]] | ||
[[Category:Construction]] | [[Category:Construction]] | ||
Latest revision as of 02:22, 25 October 2006
New hut construction
This section documents the effort to rebuild the Brew Hut.
Upcoming Events
Project Tasks
We still need help to do the following:
Completed Project Tasks
- Workhike to build outhouse and clean up garbage July 22-23, 2006
- Build Woodshed / Foundations for stairs / fly out garbage September 2006.
- Build Outhouse July 2006
- Final Workhike (for 2005) workhike October 29-30 to finish the interior and build the deck and stairs
- Remove the old hut We did this on September 24-25 weekend
- Planning-Scheduling - JP
- Prefab Construction - Roland
- Heater - Roland/Jordan
- Foundation - Rueben
- Foundation Layout - Rueben
- Sheet Metal Buying - JP (Temporary)
- Out House Prefab - Bill
- Transport - JP
- Helicopter - JP
- Build the outhouse
Other stuff
Progress Reports
- Brew Hut Minutes October 21 2004
- Brew Hut Minutes February 9, 2005
- Brew Hut Minutes March 1, 2005
- March 7 - Lumber delivered to Roland's
- March 13 - finished cutting joists; cut some studs for walls
- March 20
- March 30 - finished cutting floor insulation; painting floor
- April 4
- April 11
- April 25 - heater delivered, windows started.
- May 02
- May 21 - helicoptered material
- June 12
- June 26 - foundations finished
- July 9 to 17 - the great brew build
- July 30 - the great brew build - part 2
- September 24 - the deconstruction of the old brew hut (brew 2)
- October 29 - final 2005 workhike
New Brew Trail
A new trail is part of the plan for the new hut. See the wiki page for Brew Hut Trail Upgrade