Archive:Brew Hut Rebuild/Prefab Construction: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
imported>ScottN No edit summary |
||
| Line 10: | Line 10: | ||
* Roof framer: Cut rafters and ridge board, etc. Gussets and/or collarties and/or hurricane ties. Additional wood for this? | * Roof framer: Cut rafters and ridge board, etc. Gussets and/or collarties and/or hurricane ties. Additional wood for this? | ||
* Furnature | * Furnature | ||
==Floors== | |||
*Floor platforms complete | |||
*T&G Plywood cut, but it is low quality and has lots of little holes where knots have come out of it. | |||
*Plan to use deck paint to smooth out floor surface for both upstairs and downstairs floors | |||
*Styrofoam insulation for underneat lower floor is nearly all cut to size | |||
==Walls and Windows== | |||
*Need to decide on exact window placement before starting on framing walls | |||
*Metal door has been bought and painted | |||
*Shear strength of end walls is a concern | |||
*Wind load on the hut for high winds is unknown | |||
*Shutters for windows on main floor - upstairs as well? | |||
==Roof== | |||
*Need to purchase hurricane ties, metal roofing material and flashings | |||
==Furniture== | |||
*Table | |||
*Bench | |||
*Sleeping bench | |||
*Cooking counter | |||
*ladder | |||
*wood stove | |||
Revision as of 16:55, 22 March 2005
Currently supervised by Roland (we are working in his back yard).
Construction is usually at Saturday from 10am - 4pm and Sunday from 12pm - 4pm.
General tasks to do:
- Build walls
- Build/ buy windows
- Painting
- Roof framer: Cut rafters and ridge board, etc. Gussets and/or collarties and/or hurricane ties. Additional wood for this?
- Furnature
Floors
- Floor platforms complete
- T&G Plywood cut, but it is low quality and has lots of little holes where knots have come out of it.
- Plan to use deck paint to smooth out floor surface for both upstairs and downstairs floors
- Styrofoam insulation for underneat lower floor is nearly all cut to size
Walls and Windows
- Need to decide on exact window placement before starting on framing walls
- Metal door has been bought and painted
- Shear strength of end walls is a concern
- Wind load on the hut for high winds is unknown
- Shutters for windows on main floor - upstairs as well?
Roof
- Need to purchase hurricane ties, metal roofing material and flashings
Furniture
- Table
- Bench
- Sleeping bench
- Cooking counter
- ladder
- wood stove