==Brew Hut Rebuilding Committee Minutes==
[[Brew Hut Minutes October 21 2004]]
[[Brew Hut Minutes February 9, 2005]]
[[Brew Hut Minutes March 1, 2005]]
==New hut construction==
==New hut construction==


[[Brew Hut rebuild/Tools list | Tools list]]
This section documents the effort to rebuild the [[Brew Hut]].


==Salvageable Materials== from existing Hut
===Upcoming Events===


* 8 2x10 beams in good condition - 14 1/2 feet long
===Project Tasks===
* ladder is good - 26 inches wide by 99.5 inches tall made of 2x6 tongue and groove
* 2x6 tongue + groove boards - perhaps 50% of siding boards in existing hut are salvageable.  Tongue + groove boards on upstairs floor are poor.  These boards have already been salvaged once, so they are in short lengths and will be full of nail holes.  Tongues + grooves may become damaged during removal.
* All plywood (exterior and floor) is heavily damaged.
* Hut furniture is crude, with the exception of one nice cooking bench.
* 3 of 8 laminated beam segments are cracked.  Each beam is approx 2 1/4 inches * 6 inches.
* miscellaneous 2x8 and 2x6 boards in good shape, but already cut to short lengths.


==Helicopter Info==
We still need help to do the following:


'''Helifor Industries''' will be doing some helilogging for Terminal Forest Products in the fall (september).  They can probably move all the materials in 2 loads, and each trip is estimated to be about 15 minutes.  The going rate for this helicopter is about $5000/hr, so that makes $2500 plus ferry costs.  They can provide us with slings at no charge.  In May, they will be logging South Creek, which is about a 10 minute flight over the pemberton icefield from Brew.
* [[Brew_Hut_Rebuild/Finish the hut|Finish the hut]]


'''From Blackcomb Helicopter (Nov 2004)'''
===Completed Project Tasks===


Type of helicopters the max weight load that each of them are able to carry & costs:
* [[Brew Hut Cleanup|Workhike to build outhouse and clean up garbage]] July 22-23, 2006
*ASTAR B2 $1770.00 per hour max weight 1800 lb
* Build Woodshed / Foundations for stairs / fly out garbage September 2006.
*ASTAR BA $1570.00 per hour max weight 1500 lb
* Build Outhouse July 2006
*ASTAR B $1470.00 per hour max weight 1200 lb
* [[Brew_Hut_Rebuild/Final_Workhike|Final Workhike (for 2005)]] ''workhike October 29-30 to finish the interior and build the deck and stairs''
*Jetranger $1065.00 per hour max weight 600 lb
* [[Brew_Hut_Rebuild/Remove the old hut|Remove the old hut]] ''We did this on September 24-25 weekend''
* [[Brew Hut Rebuild/Planning-Scheduling| Planning-Scheduling]] - JP
* [[Brew Hut Rebuild/Prefab Construction| Prefab Construction]] - Roland
* [[Brew Hut Rebuild/Heater| Heater]] - Roland/Jordan
* [[Brew Hut rebuild/Foundation | Foundation]] - Rueben
* [[Brew Hut Rebuild/Foundation Layout | Foundation Layout]] - Rueben
* [[Brew Hut Rebuild/Sheet Metal|Sheet Metal Buying]] - JP (Temporary)
* [[Brew Hut Rebuild/Out House| Out House Prefab]] - Bill
* [[Brew Hut Rebuild/Transport|Transport]] - JP
* [[Brew Hut Rebuild/Helicopter|Helicopter]] - JP
* [[Brew_Hut_Rebuild/Build the outhouse|Build the outhouse]]


Time, by helicopter, from your heliport to Brew Mountain:
===Other stuff===
*.2 h from heliport to Brew Mountain one-way, .4 h return


Only the flying time that is chargeable.
* [[Brew Hut rebuild/Tools list | Tools list]]
     
* [[Brew Hut Rebuild/Salvageable Materials| Salvageable Materials]]
Other place,closer to brew mountain, where we'll be able to load our stuff (closer than your heliport):
* [[Brew Hut Rebuild/Snowpack data| Snowpack data]]
*Possibly at Brew Creek lodge with there promission
* [[Proposed Brew Hut Sign]]


'''From Black Tusk Helicopter'''
===Progress Reports===
* [[Brew Hut Minutes October 21 2004]]
* [[Brew Hut Minutes February 9, 2005]]
* [[Brew Hut Minutes March 1, 2005]]
* [[Brew Hut Rebuild/March 7|March 7]] - Lumber delivered to Roland's
* [[Brew Hut Rebuild/March 13|March 13]] - finished cutting joists; cut some studs for walls
* [[Brew Hut Rebuild/March 20|March 20]]
* [[Brew Hut Rebuild/March 30|March 30]] - finished cutting floor insulation; painting floor
* [[Brew Hut Rebuild/April 4|April 4]]
* [[Brew Hut Rebuild/April 11|April 11]]
* [[Brew Hut Rebuild/April 25|April 25]] - heater delivered, windows started.
* [[Brew Hut Rebuild/May 02|May 02]]
* [[Brew Hut Rebuild/May 21|May 21]] - helicoptered material
* [[Brew Hut Rebuild/June 12|June 12]]
* [[Brew Hut Rebuild/June 26|June 26]] - foundations finished
* [[Brew Hut Rebuild/July 9 to 17|July 9 to 17]] - the great brew build
* [[Brew Hut Rebuild/July 30|July 30]] - the great brew build - part 2
* [[Brew Hut Rebuild/September 24|September 24]] - the deconstruction of the old brew hut (brew 2)
* [[Brew_Hut_Rebuild/Final_Workhike|October 29]] - final 2005 workhike


The hourly rate on the Bell 214B Heavy Lift is $4119.50 with fuel and tax.  The flight time from Squamish to Roe Creek and back is .4 of an hour.  The flight time from Roe Creek to Mt. Brew and back to Roe Creek is .3 of an hour.  The wieght of 11000 lbs. should be pre-rigged and split into three loads.  Fuel might be needed on site at Roe Creek, and we have a fuel truck for that for an additional cost.  So .3 times three is .9,  plus a .4 for the ferry back and forth to Squamsih , for a total of 1.2 which equals $4943.40 not including the fuel truck.    Cheers. 
==New Brew Trail==
Nathan
Black Tusk Helicopter
Squamish B.C.
(604) 898-4800
flightdesk@blacktuskhelicopter.com


==Snowpack data==
A new trail is part of the plan for the new hut.  See the wiki page for [[Brew Hut Trail Upgrade]]
 
The idea here is to establish snow accumulation patterns in the area.  Any data, even annecdotal, is welcome.
 
* April 1st, 2003 -- Snow up to the top of the roof at Brew hut.  Less than 1m of snow at microbrew.
* November 14, 2004 -- 1.0m in drift near Brew Hut, no snow at microbrew (scoured by steady 60km/h winds), 50-60cm at Brew Lake.  Light winds at brew hut (sheltered from trees) and in brew lake basin.
* February 6, 2005 -- 2.5m at Brew Hut, 60cm at microbrew (wind scoured to only 20cm immediately around microbrew), 2m at flat basin above brew lake, 1.6m at Brew Lake.  Steady NW winds at Brew hut and Mircobrew.  Light NW winds at upper basin and Brew Lake.
 
==New Brew Trail==


A new trail may be part of the plan for the new hut.  See the wiki page for [[New Brew Trail]]
[[Category:Construction]]

Latest revision as of 02:22, 25 October 2006

New hut construction

This section documents the effort to rebuild the Brew Hut.

Upcoming Events

Project Tasks

We still need help to do the following:

Completed Project Tasks

Other stuff

Progress Reports

New Brew Trail

A new trail is part of the plan for the new hut. See the wiki page for Brew Hut Trail Upgrade