==Brew Hut Rebuilding Committee Minutes==
==New hut construction==


[[Brew Hut Minutes October 21 2004]]
This section documents the effort to rebuild the [[Brew Hut]].


[[Brew Hut Minutes February 9, 2005]]
===Upcoming Events===


[[Brew Hut Minutes March 1, 2005]]
===Project Tasks===


==New hut construction==
We still need help to do the following:


===Project Tasks===
* [[Brew_Hut_Rebuild/Finish the hut|Finish the hut]]


Claim something you are interested in and get it done!
===Completed Project Tasks===


* [[Brew Hut Rebuild/Prefab Construction| Prefab Construction]]
* [[Brew Hut Cleanup|Workhike to build outhouse and clean up garbage]] July 22-23, 2006
* [[Brew Hut Rebuild/Heater| Heater]]
* Build Woodshed / Foundations for stairs / fly out garbage September 2006.
* Build Outhouse July 2006
* [[Brew_Hut_Rebuild/Final_Workhike|Final Workhike (for 2005)]] ''workhike October 29-30 to finish the interior and build the deck and stairs''
* [[Brew_Hut_Rebuild/Remove the old hut|Remove the old hut]] ''We did this on September 24-25 weekend''
* [[Brew Hut Rebuild/Planning-Scheduling| Planning-Scheduling]] - JP
* [[Brew Hut Rebuild/Prefab Construction| Prefab Construction]] - Roland
* [[Brew Hut Rebuild/Heater| Heater]] - Roland/Jordan
* [[Brew Hut rebuild/Foundation | Foundation]] - Rueben
* [[Brew Hut rebuild/Foundation | Foundation]] - Rueben
* [[Brew Hut Rebuild/Sheet Metal|Sheet Metal]]
* [[Brew Hut Rebuild/Foundation Layout | Foundation Layout]] - Rueben
* [[Brew Hut rebuild/Out House| Out House]] - Bill
* [[Brew Hut Rebuild/Sheet Metal|Sheet Metal Buying]] - JP (Temporary)
* [[Brew Hut Rebuild/Transport|Transport]]
* [[Brew Hut Rebuild/Out House| Out House Prefab]] - Bill
* [[Brew Hut Rebuild/Helicopter|Helicopter]]
* [[Brew Hut Rebuild/Transport|Transport]] - JP
* [[Brew Hut Rebuild/Helicopter|Helicopter]] - JP
* [[Brew_Hut_Rebuild/Build the outhouse|Build the outhouse]]


===Other stuff===
===Other stuff===
Line 26: Line 34:
* [[Brew Hut Rebuild/Salvageable Materials| Salvageable Materials]]
* [[Brew Hut Rebuild/Salvageable Materials| Salvageable Materials]]
* [[Brew Hut Rebuild/Snowpack data| Snowpack data]]
* [[Brew Hut Rebuild/Snowpack data| Snowpack data]]
* [[Proposed Brew Hut Sign]]


==Snowpack data==
===Progress Reports===
* [[Brew Hut Minutes October 21 2004]]
* [[Brew Hut Minutes February 9, 2005]]
* [[Brew Hut Minutes March 1, 2005]]
* [[Brew Hut Rebuild/March 7|March 7]] - Lumber delivered to Roland's
* [[Brew Hut Rebuild/March 13|March 13]] - finished cutting joists; cut some studs for walls
* [[Brew Hut Rebuild/March 20|March 20]]
* [[Brew Hut Rebuild/March 30|March 30]] - finished cutting floor insulation; painting floor
* [[Brew Hut Rebuild/April 4|April 4]]
* [[Brew Hut Rebuild/April 11|April 11]]
* [[Brew Hut Rebuild/April 25|April 25]] - heater delivered, windows started.
* [[Brew Hut Rebuild/May 02|May 02]]
* [[Brew Hut Rebuild/May 21|May 21]] - helicoptered material
* [[Brew Hut Rebuild/June 12|June 12]]
* [[Brew Hut Rebuild/June 26|June 26]] - foundations finished
* [[Brew Hut Rebuild/July 9 to 17|July 9 to 17]] - the great brew build
* [[Brew Hut Rebuild/July 30|July 30]] - the great brew build - part 2
* [[Brew Hut Rebuild/September 24|September 24]] - the deconstruction of the old brew hut (brew 2)
* [[Brew_Hut_Rebuild/Final_Workhike|October 29]] - final 2005 workhike


The idea here is to establish snow accumulation patterns in the area.  Any data, even annecdotal, is welcome.
==New Brew Trail==


* April 1st, 2003 -- Snow up to the top of the roof at Brew hut.  Less than 1m of snow at microbrew.
A new trail is part of the plan for the new hut.  See the wiki page for [[Brew Hut Trail Upgrade]]
* November 14, 2004 -- 1.0m in drift near Brew Hut, no snow at microbrew (scoured by steady 60km/h winds), 50-60cm at Brew Lake.  Light winds at brew hut (sheltered from trees) and in brew lake basin.
* February 6, 2005 -- 2.5m at Brew Hut, 60cm at microbrew (wind scoured to only 20cm immediately around microbrew), 2m at flat basin above brew lake, 1.6m at Brew Lake.  Steady NW winds at Brew hut and Mircobrew.  Light NW winds at upper basin and Brew Lake.
 
==New Brew Trail==


A new trail may be part of the plan for the new hut.  See the wiki page for [[New Brew Trail]]
[[Category:Construction]]

Latest revision as of 02:22, 25 October 2006

New hut construction

This section documents the effort to rebuild the Brew Hut.

Upcoming Events

Project Tasks

We still need help to do the following:

Completed Project Tasks

Other stuff

Progress Reports

New Brew Trail

A new trail is part of the plan for the new hut. See the wiki page for Brew Hut Trail Upgrade