Archive:Brew Hut Rebuild/July 30: Difference between revisions
Jump to navigation
Jump to search
imported>Rschulz No edit summary |
imported>Dehike m Dehike moved page Brew Hut Rebuild/July 30 to Archive:Brew Hut Rebuild/July 30: Mass moving of pages, see VOCWiki:Wiki cleanup 2014-15 |
||
| (One intermediate revision by one other user not shown) | |||
| Line 4: | Line 4: | ||
There are still many small tasks to complete on the new hut and the old hut needs to be converted to firewood. | There are still many small tasks to complete on the new hut and the old hut needs to be converted to firewood. | ||
The message board thread for this trip may be found at: [http://www.ubc-voc.com/phorum2/read.php?f=1&i=9835&t=9835 July 30-August 1: Brew Hut volunteers needed!!] | |||
[[Image:NewBrewMostlyDone.jpg|thumb|left|The new Brew hut]] | [[Image:NewBrewMostlyDone.jpg|thumb|left|The new Brew hut]] | ||
Latest revision as of 22:03, 6 February 2015
Seven people went up to the hut Saturday to finish off the outside skin and to make the inside livable. Four more people came up on Sunday (carrying a few gallons of paint), increasing the workforce to eleven. This meant three or more different tasks (metal, sheeting, painting, calking) could be done at once.
All the hard work resulted in many of the finish the hut tasks being completed. The new stove was tested and the next group up to the hut can sleep in the cosy, clean hut (providing they refrain from indoor painting).
There are still many small tasks to complete on the new hut and the old hut needs to be converted to firewood.
The message board thread for this trip may be found at: July 30-August 1: Brew Hut volunteers needed!!