The | The foundations are going to be started the long weekend of Sat May 21 to Mon May 23. | ||
The week during which the construction is going to occur is no yet determine but there are several options. | The week during which the construction is going to occur is no yet determine but there are several options. | ||
Revision as of 17:07, 17 May 2005
Brew Hut Rebuilding Committee Minutes
Brew Hut Minutes October 21 2004
Brew Hut Minutes February 9, 2005
Brew Hut Minutes March 1, 2005
New hut construction
Crew sign-up
People interested in the construction should sign their name here!!!
The foundations are going to be started the long weekend of Sat May 21 to Mon May 23.
The week during which the construction is going to occur is no yet determine but there are several options. If you want to be a little bit more specific concerning your availability please use the discussion section associated with Foundation and Construction section.
- Transport material to site May 20-23 2005
- Foundation
- Construction
Project Tasks
Claim something you are interested in and get it done!
- Planning-Scheduling - JP
- Prefab Construction - Roland
- Heater - Roland/Jordan
- Foundation - Rueben
- Foundation Layout - Rueben ?
- Sheet Metal - JP (Temporary)
- Out House - Bill
- Transport - JP
- Helicopter - JP
Other stuff
Progress Reports
New Brew Trail
A new trail may be part of the plan for the new hut. See the wiki page for Brew Hut Trail Upgrade