* [[Brew Hut Rebuild/April 4|April 4]] | * [[Brew Hut Rebuild/April 4|April 4]] | ||
* [[Brew Hut Rebuild/April 11|April 11]] | * [[Brew Hut Rebuild/April 11|April 11]] | ||
* [[Brew Hut Rebuild/April 25|April 25]] | * [[Brew Hut Rebuild/April 25|April 25]] - heater delivered, windows started. | ||
* [[Brew Hut Rebuild/May 02|May 02]] | * [[Brew Hut Rebuild/May 02|May 02]] | ||
* [[Brew Hut Rebuild/May 21|May 21]] - helicoptered material | * [[Brew Hut Rebuild/May 21|May 21]] - helicoptered material | ||
Revision as of 20:53, 17 October 2005
New hut construction
This section documents the effort to rebuild the Brew Hut.
Project Tasks
We still need help to do the following:
- Finish the hut
- Build the outhouse
- Remove the old hut We did this on September 24-25 weekend
- What Remains to be Done (Oct 12)
Completed Project Tasks
- Planning-Scheduling - JP
- Prefab Construction - Roland
- Heater - Roland/Jordan
- Foundation - Rueben
- Foundation Layout - Rueben
- Sheet Metal Buying - JP (Temporary)
- Out House Prefab - Bill
- Transport - JP
- Helicopter - JP
Other stuff
Progress Reports
- Brew Hut Minutes October 21 2004
- Brew Hut Minutes February 9, 2005
- Brew Hut Minutes March 1, 2005
- March 7 - Lumber delivered to Roland's
- March 13
- March 20
- March 30
- April 4
- April 11
- April 25 - heater delivered, windows started.
- May 02
- May 21 - helicoptered material
- June 12
- June 26 - foundations finished
- July 9 to 17 - the great brew build
- July 30 - the great brew build - part 2
- September 24 - the deconstruction of the old brew hut (brew 2)
New Brew Trail
A new trail may be part of the plan for the new hut. See the wiki page for Brew Hut Trail Upgrade