==Walls and Windows== | ==Walls and Windows== | ||
*Metal door has been bought and painted. | *Metal door has been bought and painted. | ||
*One window is ready to fly; two others nearly ready; other | *One window is ready to fly; two others nearly ready; other four are being done by Scott and Ross Nelson | ||
*Shear strength of end walls is a concern. | *Shear strength of end walls is a concern. | ||
*Wind load on the hut for high winds is unknown. | *Wind load on the hut for high winds is unknown. | ||
Revision as of 16:53, 25 April 2005
Currently supervised by Roland (we are working in his back yard).
Construction is usually at Saturday from 10am - 4pm and Sunday from 12pm - 4pm.
General tasks to do:
- Build walls
- Build/ buy windows
- Painting
- Roof framer: Cut rafters and ridge board, etc. Gussets and/or collarties and/or hurricane ties. Additional wood for this?
- Furnature
Floors
- Floor platforms, joists are all cut to size.
- T&G Plywood cut, but it is low quality and has lots of little holes where knots have come out of it.
- Attic floor has now been painted with 3 coats of urethane paint.
- Main floor will be painted with urethane plus non-slip additive.
- Styrofoam insulation for underneath lower floor has been cut to size.
Walls and Windows
- Metal door has been bought and painted.
- One window is ready to fly; two others nearly ready; other four are being done by Scott and Ross Nelson
- Shear strength of end walls is a concern.
- Wind load on the hut for high winds is unknown.
- Shutters for windows on main floor - upstairs as well?
Roof
- Need to purchase hurricane ties, metal roofing material and flashings
Furniture
- Table
- Bench
- Sleeping bench
- Cooking counter
- ladder
- wood stove