Weather was wet this weekend. On Saturday, JP and Karine painted interior walls in the cramped cold space under the back porch, to get away from the rain. Rueben and Marie re-stacked wood and cut some interior wall sheathing. Roland cut rafters. We took apart the attic platform as it is now finished enough and ready to fly.

On Sunday, Soren sanded window parts and stacked wood. Roland cut rafters. We bough some more mis-tint paint to paint the main floor as soon as it stops raining (ikely 3pm Monday today). All rafters are now cut to length.

Rueben reports that his dad has built us an out-house, and it will probably have a stained glass window in it.

This week we plan to resolve all remaining sheet metal isues, with a trip out to the big store in (Langley?).