Phelix Creek Trail Construction

From VOC Wiki
Revision as of 03:50, 24 October 2007 by imported>Rschulz (October 20-21:: added a link to my photos)
Jump to navigation Jump to search

In July 2007 the VOC received permission to build a proper trail up to the Brian Waddington Hut.

Workhikes Completed

Jan 27-28:

A scouting mission. A small VOC party skiied up with lots of flagging tape to get the route "just right" for skiis. Fun was had skiing around the hut afterwards.

June 23-24:

Another scouting mission. A slightly larger VOC party went up to determine which areas would be highly disastrous and wet during spring runoff conditions. It was discovered that there is alot of slide alder on the West side of Phelix creek in the open, lots of huge blowdowns everywhere in the forest, and snow remaining on the ground starting at the third major slide path.

July 21-22:

A brushing mission. 12 VOCers with 5 pruners, 6 bow saws, an axe and 2 chainsaws did a lot of work. The first two slide paths are now totally brushed out, and the first blow down area cleaned up. The third slide alder path is mostly complete, with some chainsaw work remaining. The forest after this point was intermittently cleared to the first switchback. Finally a large section of blow down / brush was cleared in between the first and second switchbacks, except for an unavoidable boggy patch.

At the hut, a temporary bridge across the creek beside the hut was fashioned by laying down blow downs carried to the site and lashing them together with steel cable. Also, the poop shoot in the outhouse was re-aligned.

Remaining work includes planning and clearing the first and second switchbacks, figuring out what to do with the boggy section, and clearing the long stretch up from the second switchback to the snow line. We must wait and see what lies under the snow after this point to make further decisions. The bridge should also be made more permanent by bolting the logs to the rock, and adding expanded steel sheet or metal lath for traction.

July 28-29:

A solo mission. Christian carried up the hardware for the bridge, and installed it. The two logs from last weekend are bolted directly to the boulders on either side of the river, and expanded metal lath added for traction. The second switchbacks were also flagged out, avoiding the wet and swampy areas.

August 4,5,6:

Part 2 of the brushing mission. Saturday We set the route on the first switchback section and the bench, then bushed it out and started brush clearing on the second switchback section where Christian had previously flagged it. Several non-VOC people found there way up the trail and helped out with the clearing work when they reached the front line. Monday saw the completion of route setting and flagging on the second switchback section and brushing out most of the second switchback section. Brushing is now completed continuously from the start of the trail to just above the upper boulder field at 1600m. The remaining trail from that point to the lake has been flagged in detail.

Oct 6-7:

Not really a workhike, more of a regular trip and recon, but some clipping was done. Found 5" of snow at the uncompleted section of the new trail. Also noted some minor issues with the hut (door, broom, mice). Weather was terrible, but the rain on Sunday did start to melt the pesky snow.

October 20-21: